Critical control verification (CCV) checklists for structural collapse and demolition: one four-page CCV form for each of the 6 critical controls that stop the unwanted event, structure, part of a structure or temporary works collapses unexpectedly, or limit the harm when it happens, with the bowtie, a verification schedule and a guide.

  • HazardDemolition, alteration and temporary works
  • Unwanted eventStructure, part of a structure or temporary works collapses unexpectedly
  • Critical controls6: 4 preventing, 2 mitigating
  • FormsOne four-page CCV form per control, the bowtie, a CCV schedule and a guide
  • Task or hazardManaging critical risks
  • JurisdictionNational: check licences and notifications with your regulator
  • FormatsWord and Excel, editable, with PDF copies
  • CodeDOC-STR-CCV
  • Version1.0 · 3.7 MB ZIP

What is this pack?

The Structural Collapse and Demolition Critical Control Verification Pack is a set of editable critical control verification (CCV) checklists for demolition and structural collapse risks in Australian workplaces, for WHS advisers, managers, supervisors and control owners. It covers 6 critical controls (4 preventing, 2 mitigating) for the unwanted event: structure, part of a structure or temporary works collapses unexpectedly. It includes 6 four-page CCV forms in Word and PDF, one for each critical control; the Structural Collapse and Demolition Bowtie on one page; the CCV schedule in Word, PDF and Excel; and the guide How to Use These CCVs. It draws on the model Code of Practice Demolition work, cited by title. It supports verification; it is not legal advice.

The 6 critical controls

  1. CCV-01 Demolition done in the engineer's sequence, with hold points checked (preventing)
  2. CCV-02 Temporary works designed, installed and inspected before loading, removed only with approval (preventing)
  3. CCV-03 Floor and platform load limits kept (preventing)
  4. CCV-04 Elements of unknown or weakened condition propped or isolated before work (preventing)
  5. CCV-05 Exclusion zone around the collapse and drop zone kept clear (mitigating)
  6. CCV-06 Emergency response for collapse and entrapment (mitigating)

About this pack

Most workplaces have controls for structural collapse and demolition: the engineer's sequence, propping, formwork inspections, load limits and exclusion zones. The question is whether they are working today. A critical control verification (CCV) is the proof: a planned check, in the field, that a control that matters most is in place, in good condition, working as designed, used properly and not bypassed.

This pack gives you one CCV form for each of 6 critical controls (4 preventing, 2 mitigating). Each form shows where the control sits on the bowtie, what it must achieve, how it fails, and a checklist grouped by those five checks and then the records. The last page has prompts for talking to the people who use the control.

Every item is Pass or Fail; Non-conformance is kept for administrative items such as records and training dates, and its box is greyed out on the rest. A Fail stops the work that relies on the control and is escalated as a high potential incident. The download holds 6 four-page CCV forms in Word and PDF, one for each critical control; the Structural Collapse and Demolition Bowtie on one page; the CCV schedule in Word, PDF and Excel; and the guide How to Use These CCVs.

Where it applies: Demolition, partial demolition, strip-out and alteration of buildings and structures, and construction work that relies on temporary works: propping, formwork, falsework, bracing and back-propping.

What it helps you do

  • Prove, not assume, that the 6 critical controls for structural collapse and demolition are in place and working
  • Score each control the same way every time: Pass, Fail, or Non-conformance for administrative items only
  • Act at once on a Fail, and close every Non-conformance with an owner and a date
  • Hear from the people who use each control where it is skipped or hard to use
  • Report CCV results as a leading indicator, alongside incident data

Each checklist is grouped by

  • It exists: it is there, at this place, for this work, today
  • It is in place and in good condition
  • It functions as designed
  • It is being used properly
  • It is not being bypassed or failing silently
  • Records and administration

The critical controls

Each has its own four-page CCV form. Preventing controls sit on the threat lines of the bowtie and stop the unwanted event; mitigating controls sit on the consequence lines and limit the harm. A control on both sides is one control, verified for both roles.

CCVCritical controlTypeSits onChecklist items
CCV-01Demolition done in the engineer's sequence, with hold points checked
Keep the structure stable at every stage of demolition by removing elements only in the sequence the engineer or competent person sets, with each hold point checked and released before the next stage starts.
PreventingT19 (2 administrative)
CCV-02Temporary works designed, installed and inspected before loading, removed only with approval
Make sure propping, formwork, falsework, bracing and back-propping are designed for the loads, installed as designed, inspected by a competent person before they are loaded, and removed only when the engineer or competent person approves.
PreventingT29 (2 administrative)
CCV-03Floor and platform load limits kept
Keep loads on floors, slabs and platforms within [Floor load limit]: debris cleared regularly, materials spread, and plant used on a structure only where the engineer confirms it can carry it.
PreventingT3, T59 (2 administrative)
CCV-04Elements of unknown or weakened condition propped or isolated before work
Before work near elements whose condition or design is unknown or weakened (deteriorated concrete, rusted steel, unreinforced masonry, post-tensioned or prestressed members), have them assessed by an engineer and propped, de-stressed or isolated as the engineer directs.
PreventingT49 (2 administrative)
CCV-05Exclusion zone around the collapse and drop zone kept clear
Keep workers, other trades and the public out of the area where the structure, or part of it, would land if it fell, with barricades, signs and a person controlling entry during high-risk stages.
MitigatingC1, C39 (2 administrative)
CCV-06Emergency response for collapse and entrapment
If part of a structure collapses, raise the alarm, account for everyone, call emergency services, keep untrained people out of the unstable area, and give first aid to those who can be reached safely.
MitigatingC1, C29 (2 administrative)

Threats

  • T1 Demolition out of sequence: load-bearing parts removed too early
  • T2 Temporary works inadequate, altered or removed too early
  • T3 Floors, slabs or platforms overloaded with debris, plant or materials
  • T4 Unknown condition: deterioration, hidden defects, post-tensioned or prestressed elements
  • T5 Plant working on or against the structure beyond what it can take

Consequences

  • C1 Workers killed
  • C2 Workers trapped or seriously injured
  • C3 Members of the public or neighbouring property struck

Supporting controls, shown dashed on the bowtie with no CCV form: Hoardings and overhead protection at public areas (on C3).

How each form is scored

The same rules in every pack. The worst item decides the overall result.

MarkWhen
PassYou saw it in place and working, today. A Pass is something you saw, not something you remembered or were told.
FailIt is not in place, or it does not work, or it is bypassed. On an administrative item, use Fail only when what you found means the control itself is not there (for example, nobody on the shift is authorised to operate).
Non-conformance (NC)Administrative items only. The control is in place and working, but a supporting element is missing, late or incomplete: a record, a training date, a review date. Fix it as an action.

Non-conformance is offered only on administrative items: records, training currency, plan and review dates, things that would not on their own cause the unwanted event straight away. Every other item checks that the control is physically there and working, so it is Pass or Fail only: its NC box is greyed out.

Overall resultWhenWhat happens
PASSEvery item PassIn place and effective. Record it in the CCV schedule, and check it against hazard reports, near misses and incidents for this control.
NON-CONFORMANCENo Fail; one or more NCIn place, not fully effective. A temporary control first if needed; an action for each NC, with an owner, closed within 30 days. Tell the supervisor and control owner this shift. A repeat NC is investigated.
FAILAny item FailNOT effective. Stop the work that relies on it, make it safe, and tell the supervisor and the escalation contact now. Report it as a high potential incident. Restart only when the control, or a temporary control the risk owner accepts, is in place and verified again.

Talk to the people

The fourth page of every form: five or six prompts written for that control. Talk to at least two people who use, maintain or supervise this control, on the job and in their own words. Ask open questions and listen: they know where it gets skipped, worked around or is hard to use.

  • Anything that suggests the control is missing, bypassed or not working is checked in the field straight away and scored; confirmed, it is a Fail.
  • Everything else that matters goes in the comments, and each thing to fix becomes an action with an owner and a due date.
  • The people spoken to are told what will happen with what they said, and it is never used against them.

What is included

Delivered as one ZIP download. The files below are editable, and the Word documents also come as PDFs. Each download also includes Read Me First, a Product Overview, the Permitted Use Terms and Version Information (PDF).

FileFormatWhat it is for
How to Use These CCVsWord (.docx)The guide: what a CCV is, how to verify and score, the response to a Fail or Non-conformance, frequency, and how to adapt the pack to your site.
Structural Collapse and Demolition BowtieWord (.docx)Every threat, consequence and critical control on one landscape page, with its key: which controls prevent, which mitigate, which work on both sides, and the supporting controls.
CCV-01 Demolition done in the engineer's sequence, with hold points checkedWord (.docx)A four-page field form for one critical control: its bowtie, objective, performance requirements and failure modes, the checklist (Pass, Fail, and Non-conformance on administrative items only), the overall result, actions, talk to the people, and sign-off.
CCV-02 Temporary works designed, installed and inspected before loading, removed only with approvalWord (.docx)A four-page field form for one critical control: its bowtie, objective, performance requirements and failure modes, the checklist (Pass, Fail, and Non-conformance on administrative items only), the overall result, actions, talk to the people, and sign-off.
CCV-03 Floor and platform load limits keptWord (.docx)A four-page field form for one critical control: its bowtie, objective, performance requirements and failure modes, the checklist (Pass, Fail, and Non-conformance on administrative items only), the overall result, actions, talk to the people, and sign-off.
CCV-04 Elements of unknown or weakened condition propped or isolated before workWord (.docx)A four-page field form for one critical control: its bowtie, objective, performance requirements and failure modes, the checklist (Pass, Fail, and Non-conformance on administrative items only), the overall result, actions, talk to the people, and sign-off.
CCV-05 Exclusion zone around the collapse and drop zone kept clearWord (.docx)A four-page field form for one critical control: its bowtie, objective, performance requirements and failure modes, the checklist (Pass, Fail, and Non-conformance on administrative items only), the overall result, actions, talk to the people, and sign-off.
CCV-06 Emergency response for collapse and entrapmentWord (.docx)A four-page field form for one critical control: its bowtie, objective, performance requirements and failure modes, the checklist (Pass, Fail, and Non-conformance on administrative items only), the overall result, actions, talk to the people, and sign-off.
CCV ScheduleWord (.docx)Who verifies each control, how often by exposure, the method and the record: in Word, and as an Excel workbook with suggested frequencies, next due dates and status by formula.
CCV ScheduleExcel (.xlsx)Who verifies each control, how often by exposure, the method and the record: in Word, and as an Excel workbook with suggested frequencies, next due dates and status by formula.

The technical content paraphrases, and cites by title, Safe Work Australia's model Codes of Practice Demolition work, Construction work and Safe design of structures, the Australian Standards for demolition and formwork your business uses, and your engineer's advice. Demolition licences and notifications differ between jurisdictions: check with your regulator. Nothing is copied.

Questions about this pack

What is a critical control verification (CCV)?

A planned check, in the field, that one critical control is doing its job: that it exists, is in place and in good condition, functions as designed, is used properly and is not bypassed or failing silently. It is proof, not assumption. It is not a general inspection or audit: it tests one control, in depth, against what it must achieve. A CCV form, or CCV checklist, is the record of that check.

Which critical controls are in the Structural Collapse and Demolition pack?

6 critical controls (4 preventing, 2 mitigating) for the unwanted event: structure, part of a structure or temporary works collapses unexpectedly. CCV-01 Demolition done in the engineer's sequence, with hold points checked; CCV-02 Temporary works designed, installed and inspected before loading, removed only with approval; CCV-03 Floor and platform load limits kept; CCV-04 Elements of unknown or weakened condition propped or isolated before work; CCV-05 Exclusion zone around the collapse and drop zone kept clear; CCV-06 Emergency response for collapse and entrapment.

What is a bowtie, and is it included?

A bowtie is a one-page diagram of a risk: the threats that could cause the unwanted event on the left, the consequences on the right, and the critical controls on each line. The Structural Collapse and Demolition Bowtie is included in Word and PDF, so you can use it as an editable bowtie template for your site, and each CCV form shows where its control sits on it.

How is a CCV scored?

Pass or Fail on every item. Non-conformance is offered only on administrative items: records, training currency, plan and review dates, things that would not on their own cause the unwanted event straight away. Every other item checks that the control is physically there and working, so it is Pass or Fail only: its NC box is greyed out. Any Fail means the control is not effective: the work that relies on it stops, and it is escalated as a high potential incident. A Non-conformance gets a temporary control if needed and an action closed within 30 days; a repeat is investigated.

What is on the last page of each form?

Talk to the people: five or six prompts written for that control, for the operators, workers and supervisors who use it: what they actually do, when it gets skipped or is hard to use, what has changed, and what they would fix. Anything that suggests the control is missing, bypassed or not working is checked in the field straight away and scored; confirmed, it is a Fail. Everything else that matters goes in the comments, and each thing to fix becomes an action with an owner and a due date.

How often should critical controls be verified?

The CCV schedule (verification schedule) sets how often each critical control is verified, by the exposure where it is used: high (daily exposure, many people or vehicles), medium (weekly, or few people) or low (an occasional task). The guide gives weekly, monthly and quarterly as starting points; each control's own frequencies are set in the schedule. Verify a control in every place it is used, in turn, and more often after a Fail, a near miss or a change, and while an action is open.

Is this pack suitable for my state?

Yes, anywhere in Australia. It is national, written for the WHS and OHS laws generally, with the model Code of Practice Demolition work and other guidance cited by title. Your state or territory may have approved the codes with changes, and some requirements, such as licences, notifying the regulator and registering plant, differ between jurisdictions: check with your regulator. Victoria has its own Occupational Health and Safety Act 2004 and regulations, and WorkSafe Victoria publishes its own guidance.

Can we change the forms?

Yes. Every form, the bowtie and the schedule are editable Word and Excel files: add your logo and business name, your site's limits, plant and roles, delete items that do not apply and add your own. The guide says what to adapt, and how to decide whether a new item may offer Non-conformance.

Is it legal advice, or the same as an audit?

No. These forms help your business prove that its critical controls are in place and working. They do not do that on their own: adapt them to your site, plant and people, verify in the field, and act on what you find. The forms are general information, not legal advice. Work health and safety law differs between jurisdictions and changes over time. Check the requirements that apply where you operate.

Is GST included in the price?

Yes. Every price in the store includes GST, so $149.00 is the total, including $13.55 GST. Your receipt is a tax invoice showing the GST.

How are the files delivered?

As a ZIP download. Card purchases can be downloaded straight away from the confirmation page and by a link we email you. Download links expire after 14 days for security; you can request a new one at any time.

Can we use it at more than one site?

Yes, across your own organisation. The pack is licensed for internal use by the purchasing organisation. A consultant using it with clients needs separate written permission.

What is your refund policy?

Your rights under the Australian Consumer Law are not affected. See the Refund Policy for how we handle a product that is faulty, not as described, or not what you ordered.

Legal information here is general. It may not be correct in your jurisdiction: please check with your local WHS or OHS regulator.

Ordering for a business or several sites? Request an invoice. Other questions: contact us.

Goes with

The audit tools for the code of practice. The plan that sets up the critical risk program these forms verify. The Critical Control Management training packages.

Demolition Work Code of Practice Audit Tool

For: WHS advisers, managers, supervisors and health and safety representatives

An Excel audit tool for the code of practice Demolition work, with 35 referenced questions, automatic scores, a dashboard, corrective actions, a field checklist and a report template.

What's included
  • 35 referenced audit questions in 5 chapters
  • Excel workbook with automatic scoring, a dashboard and corrective actions
  • Field audit checklist and audit report template (Word and PDF)
  • Guide: how to rate, evidence and follow up

Construction Work Code of Practice Audit Tool

For: WHS advisers, managers, supervisors and health and safety representatives

An Excel audit tool for the code of practice Construction work, with 29 referenced questions, automatic scores, a dashboard, corrective actions, a field checklist and a report template.

What's included
  • 29 referenced audit questions in 7 chapters
  • Excel workbook with automatic scoring, a dashboard and corrective actions
  • Field audit checklist and audit report template (Word and PDF)
  • Guide: how to rate, evidence and follow up

Safe Design of Structures Code of Practice Audit Tool

For: WHS advisers, managers, supervisors and health and safety representatives

An Excel audit tool for the code of practice Safe design of structures, with 25 referenced questions, automatic scores, a dashboard, corrective actions, a field checklist and a report template.

What's included
  • 25 referenced audit questions in 4 chapters
  • Excel workbook with automatic scoring, a dashboard and corrective actions
  • Field audit checklist and audit report template (Word and PDF)
  • Guide: how to rate, evidence and follow up

Critical Risk Management Plan

For: Australian businesses with work that could kill or seriously injure someone, and the officers, managers, supervisors and WHS advisers who manage those risks

A complete, editable critical risk management plan for Australian businesses: find the risks that could kill, map them with bowties, define, own and verify the critical controls, aligned to the model WHS laws and ISO 31000.

What's included
  • The critical risk management plan, a policy, and a roles and accountabilities guide with officers' due diligence
  • A broad-brush workshop guide, an Excel critical risk register that tiers and ranks each risk on the same risk matrix as the WHS plans, and a drawn bowtie template
  • A critical control selection checklist, performance standard template, control owner accountability statement and Excel critical controls register
  • An Excel verification program and schedule, a generic verification form scored Pass, Fail or Non-conformance, an officers' report, a failure response procedure and a dashboard

Training: Critical Control Management Practitioner · Critical Control Management Implementation Toolkit